Dredging Update – March 9, 2017
The Bay Dredging project is 77% complete with 74,912 CY dredged as of March 8th. South [...]
The Bay Dredging project is 77% complete with 74,912 CY dredged as of March 8th. South [...]
Stone Harbor Mayor Judith Davies-Dunhour, Council Members Joselyn Rich and Ray Parzych, Administrator Jill Gougher, Public [...]
This update provided by SHPOA Beach & Bay Committee The dredge “Texas” arrived February 14th, 2017 and [...]
Officials from Avalon and Stone Harbor attended the weekly progress meeting for the upcoming beach [...]
By Wally Bishop, Chair SHPOA Beach & Bay Committee Borough Officials have confirmed that the necessary [...]
Per the Daily Progress Report posted on the SH Borough website (www.stoneharbornj.org), Sevenson Environmental has updated [...]
The Army Corps contract to replenish the SH beach has been halted due to regulatory and [...]
Updated Information as of October 12, 2016
According to Jill Gougher, Borough Administrator - " ... Sevenson has received both the DEP and [...]
The Corps of Engineers has issued a public notice soliciting comments regarding a request by the [...]